Public support must not be paid twice
Renovabene explains that subsidies must be deducted from the relevant additional-benefit amount. Publicly covered costs should not again form the basis for rent pass-through. This accounting rule is different from promising every subsidised project will have no rent increase.
The PCP supports presenting gross costs, maintenance, grants and remaining investment separately. If the final grant differs from an estimate, the final account must show the adjustment rather than letting a provisional assumption disappear from scrutiny.
Less energy does not always mean cheaper housing
Consider a purely hypothetical illustration, not a legal rent calculation: net rent rises by CHF 120 monthly and energy spending falls by CHF 60. Consumption can decline while total housing cost rises by CHF 60.
Physical saving differs from energy price. Fewer kilowatt-hours produce different amounts depending on tariff, weather and use. An advance estimate cannot guarantee the first bill. The PCP calls for explicit assumptions and post-commissioning checks to correct technical faults.
For an already constrained household, even a modest increase can jeopardise remaining. Social assessment therefore needs total costs and available resources, not merely a building-wide energy percentage.
Address investment capacity without erasing ability to pay
Owners finance work before future savings and revenue arise. Grants, loans and technical support can unlock useful projects. Denying that constraint would slow renovation. But transferring every risk to tenants is no fair solution.
The PCP supports public assistance with social commitments within the competent framework: transparent pass-through, affordable use and protection during transformation. These are political proposals, not uniform conditions already attached to every cantonal subsidy.
Match works to the building and the life within it
Comprehensive renovation can coordinate interventions and avoid repeated work. Staging spreads investment and can preserve occupancy. Each has constraints involving disruption duration, access, interruptions and technical coherence.
The PCP calls for comparing alternatives with a retention or, where necessary, temporary-rehousing plan. Moving expense and uncertainty about returning are social costs. Neither the most ambitious technical option without consequences assessed nor a minimal intervention used as indefinite postponement is sufficient.
Residents need information before construction
Late involvement presents tenants with closed decisions. Information should explain timing, disrupted uses, alternatives and estimated financial effects. Residents can also identify ventilation, damp or usage problems not fully captured in technical documents.
Support needs working time and an identifiable contact, not merely a general notice. Vulnerable people require preparation suited to their situation; the same interruption can have very different consequences.
Execution quality protects the budget too
Equipment efficient on paper can be poorly adjusted or maintained. Acceptance testing, balancing and understandable controls shape results. The PCP supports financing those duties under workable employment conditions.
Stable programmes help companies train and retain qualified teams. Lowest-price competition can generate rework, faults and future costs. Scrutiny must address delivered quality and correction responsibilities alongside the initial price.
Improve buildings without replacing their population
Public, cooperative and cost-rent housing offer specific means to connect investment and affordability. The PCP supports their expansion with lasting funding and understandable maintenance and renewal accounts.
Across rental housing, two goals should be verifiable: reduced energy needs and preserved affordability. Public support should connect them. Successful renovation creates a more efficient, properly operated building that remains habitable for the people housing policy should serve.
Documents and sources
- Office fédéral du logement — Logement et pénurie d’énergie
- Renovabene — Quels coûts les bailleurs peuvent-ils répercuter sur les loyers après un assainissement ?
- Renovabene — L’assainissement doit-il être réalisé de manière échelonnée ou en une seule étape ?
- Confédération et cantons — Bilan 2025 du Programme Bâtiments